Decision to outsource

  • June 2018 Cabinet decision to commence procurement
  • Sept 2018 Briefing to staff and stakeholders

Tenders

  • Aug-Dec 2018 Prepare Service Level Agreements, contract documentation, evaluation framework, project team
  • Jan 2019 Finalise documents, publish OJEU invitation to tender
  • March 2019 Closing date, shortlist (minimum 5) to invite to tender
  • May 2019 Closing date for submission of bid

Evaluation

  • Nov 2018 Staff and stakeholder evaluation groups established.
  • July/2019 Evaluation and moderation panels
  • Aug 2019 Staff and stakeholder group input
  • Oct 2019 Panel make final selection (moderation)

Award Contract

  • Nov 2019 HC prepare governance papers
  • Dec 2019 Option for scrutiny committee
  • Jan 2020 Decision to award contract by Cabinet Member
  • March 2020 Finalise contract

Implementation

  • Feb- June 2020
  • July 2020 New Contract Commences